University Village Apartments, Phase II

 

 

This project will provide 888 beds as a second phase of student housing; the project will also include space for resident advisors, dining facilities and community facilities.  The structure will be built on existing Parking Lot O and may include renovations of the existing commons building and grounds.

 

Funding:

System-wide Revenue Bond

 

Estimated Total Project Cost:

$100,000,000

 

Estimated Construction Cost:

$82,000,000

 

Project Manager:

Brad Fenton, AIA, LEED, AP

(760) 750-4659

bfenton@csusm.edu

Architect:

Feasibility: MVE Institutional

(www.mve-institutional.com)

 

Contractor:

TBD

 

Current Status:

Feasibility Study

 

Schedule:

Feasibility Study Completion: July 2008

Last Updated:

June 12, 2008

 

Office of Planning, Design and Construction

Craven Hall 5111

333 So. Twin Oaks Valley Rd.

San Marcos, CA 92096-0001

 
"Becoming nationally recognized leaders in higher ed administration"
 

PDC Home | CSUSM Home | CSUSM Search | Help for this Site | Last Revised: 06/12/2008