Business and Financial Services Campus Enterprises Facilities Development and Management Human Resources and Risk Management University Police Vice President
Planning, Design and Construction

Social and Behavioral Sciences Building

 

Campus Photo   Campus Photo

              View from west end of the building                                     View from east end of the building

 

This project will build a 106,509 square foot (67,438 ASF) classroom/office building that will house the Social and Behavioral Sciences programs.  The building will provide 739 seats with 461 FTE in Lecture, 51 FTE in Lower Division Lab, 132 FTE in Upper Division Lab, Graduate Research Space, 125 Faculty Offices, Dean’s Suite, 10 Department Suites, Support Spaces, Conference Rooms, and 2 centers.  The programs that will be housed in the SBSB are: Psychology, Sociology, Communication/Mass Media, Economics, Political Science, Anthropology, Liberal Studies, and Human Development.

 

Funding:

Major Capital 2006-2007

 

Total Project Cost:

$56,842,000

 

Construction Cost Estimate:

$43,132,000

 

Sitework Cost:

$2,250,000

 

Project Manager:

Diane Malone, AIA, LEED, AP

(760) 750-4658

dmalone@csusm.edu

Architect:

AC Martin Partners

(www.acmartin.com)

 

Contractor:

Sitework: TBD

Building Construction: TBD

 

Current Status:

Sitework: Bidding

Building Construction: Construction Documents

 

Schedule:

Sitework - Start: July 2008

Sitework - Completion: November 2008

 

Building Construction - Out to Bid: October 2008

Building Construction - Bid Date: November 2008

Building Construction - Start: December 2008

Building Construction - Completion: August 2010

Occupancy: January 2011

 

Last Updated:

June 18, 2008

 

Office of Planning, Design and Construction

Craven Hall 5111

333 So. Twin Oaks Valley Rd.

San Marcos, CA 92096-0001

 
"Becoming nationally recognized leaders in higher ed administration"
 

PDC Home | CSUSM Home | CSUSM Search | Help for this Site | Last Revised: 06/18/2008