This project is the first of at least six planned parking structures on the campus for full development. The structure will be built on the existing 577 space Lot N.  The structure was originally approved for the 2007/08 Capital Outlay Program for 2,800 spaces and will be built in two phases. The first phase structure will provide 1,615 spaces to support the growth in FTES.
 
The delivery method for this project will be broken into two phases. Phase One will consist of a traditional design-bid-build delivery method for the site improvements. Phase Two will consist of the parking structure that will be design-build.
 

Funding:

System-wide Revenue Bond

 

Total Project Cost:

CVDE (Phase 1): $3,264,000

Structure (Phase 2): $29,898,000

 

Construction Cost:

CVDE (Phase 1): $2,365,000

Structure (Phase 2): $24,052,000

 

Project Manager:

Bradly Fenton, AIA, LEED, AP

(760) 750-4659

bfenton@csusm.edu

Architect:

Phase 1: RBF Consulting (www.rbf.com)

Phase 2: RJC Architects / Graelic

 

Contractor:

Phase 1: Western Rim

Phase 2: PCL Construction Services

 

Current Status:

Phase 1: Approved

Phase 2: Pending BOT Approval

 

Schedule:

Phase 1 - Construction Start: August 2008

Phase 1 - Construction Completion: February 2009

 

Phase 2 - Design Start: July 2008

Phase 2 - Construction Start: March 2009

Phase 2 - Construction Completion: July 2010

 

Last Updated:

June 12, 2008

 

Office of Planning, Design and Construction

Craven Hall 5111

333 So. Twin Oaks Valley Rd.

San Marcos, CA 92096-0001

 
"Becoming nationally recognized leaders in higher ed administration"
 

PDC Home | CSUSM Home | CSUSM Search | Help for this Site | Last Revised: 06/12/2008