ESCO projects implement various energy conservation improvements, including work in the science buildings to modify controls and improve ventilation, change interior and exterior lighting, and make revisions to the Central Plant.  This work will primarily affect Faculty and research staff in the science buildings during July and August.  More detailed coordination/information will be provided on a case-by-case basis regarding affected rooms.  Lighting upgrades will take place after normal working hours beginning in August and will continue for several months.

 

Funding:

Equipment Lease Financing/ Utility Savings Increases

 

Estimated Total Project Cost:

$ 7,800,000

 

Estimated Construction Cost:

$ 7,800,000

 

Project Manager:

Russell Decker

(760) 750-4653

rdecker@csusm.edu

 

Architect/Engineer:

DMJM Harris (and Consultants)

 

Contractor:

DMJM Harris (Design-Build)

 

Current Status:

Construction

 

Schedule:

Construction Completion: December 2008

Last Updated:

July 22, 2008

 

Office of Planning, Design and Construction

Craven Hall 5111

333 So. Twin Oaks Valley Rd.

San Marcos, CA 92096-0001

 
"Becoming nationally recognized leaders in higher ed administration"
 

PDC Home | CSUSM Home | CSUSM Search | Help for this Site | Last Revised: 07/22/2008