AIRBORNE IRRITANTS

ODOROUS AND TOXIN MATERIALS NOTIFICATION PROCEDURE    Spray Can          

The purpose of this procedure is to advise the campus community when materials are used inside buildings which either contain toxins or emit odor. The campus will receive notification via the Facility Services’ website: http://www.csusm.edu/facilities/AirborneIrritants.htm  All posting will be made 48 hours prior to the use of the material, except for emergencies. Materials include but are not limited to the use of all insecticides, paint, and carpet glues. See Schedule Below

Facility staff will email the website administrator and the work control coordinator this information:  schedule date, exact location for treatment, procedure and substance used.   If this schedule is missed, then Facility Services staff must reschedule work to allow proper notification. There are no exceptions to this process except for emergencies. The work control coordinator will post this information to the Facility Services’ Web site daily by 5 p.m. as needed. As an added precaution, Facility Services will be using non-VOC paint to minimize irritations. Non-VOC paint is designed specifically for classrooms and hospital environments.

Management must approve emergencies.  Management will coordinate with Human Resources for all emergency situations. The website administrator will post the notice as emergency after approval from Human Resources.

For pest infestation, all efforts will be made to schedule pest control treatment after 5:00 pm. However, in extreme situations of pest infestation, it may be necessary to treat the situation sooner. If quick treatment is necessary, the situation will be considered an emergency and coordinated through Human Resources.  Facility Services’ staff will try to mitigate pest infestations before using the pest control services during working hours.

This procedure was created to ensure the health and safety of the campus community and in consideration of those who have sensitivity to toxins and odorous materials.  

ODOROUS AND TOXIN MATERIALS SCHEDULE

POST DATE SCHEDULE DATE LOCATION PROCEDURE SUBSTANCE
1/9/06 1/11/06 THRU 1/12/06 ARTS 390 PAINT PAINT
1/10/06 1/12/06 THRU 1/16/06 KEL 1106, 1107, 1108, 1109 & 1111 PAINT PAINT
1/11/06 1/14/06 MH 3rd and 4th FLOOR ELEVATOR LOBBY PAINT PAINT
1/13/06 1/17/06  THRU 1/20/06 UH 221 PAINT PAINT
1/24/06 1/26/06  THRU 1/27/06 ARTS-302 & 2ND FLOOR MAIN ENTRY TILE SETTING ADHESIVE
1/24/06 1/26/06  THRU 1/31/06 LIB-2415, 2417, 2436, 2437, 4106, 4407, 5108, 3200 (EXHIBIT AREA) & 3301 (NEAR RESTROOM) PAINT PAINT
1/24/06 1/27/06 UH-297, 291, 491 & 391 DOORS PAINT PAINT
1/24/06 2/2/06 & 2/7/06 SCI I-122, 120 EXTERIOR DOORS & CORRIDOR 105 DOORS & FRAMES PAINT PAINT
1/24/06 1/30/06  & 2/7/06 COM-LOADING AREA 111D EXTERIOR DOORS, FRAMES & WINDOWS & CORRIDOR C101 PAINT PAINT
1/26/06 1/30/06 & 1/31/06 USB-HALLWAY #68 (NEAR KITCHEN AREA) CARPET LAYING ADHESIVE
2/8/06 2/9/06 THRU 2/10/06 MH-THROUGHOUT BUILDING PAINT PAINT
2/9/06 2/13/06 THRU 2/17/06 CRA-2ND FLOOR PAINT PAINT
2/15/06 2/16/06 THRU 2/17/06 SCI2 1ST & 3RD FLOOR (HALLWAY IN FRONT OF RM120 HALLWAY IN FRONT OF RM 320) FLOOR ADHESIVE ADHESIVE
2/16/06 2/20/06 THRU 3/03/06 FIELD HOUSE MAIN LOBBY, STE. 106 OFFICES E THRU K PAINT PAINT
2/16/06 2/20/06 THRU 2/22/06 CRA-2ND FLOOR PAINT PAINT
2/21/06 2/21/06 THRU 2/28/06 FCB 5-110 ,6-102a, 6-104a 6-106, 6-105, 6-101, 6-103, 6-102, 6-104 PAINT EXTERIOR DOORS AND FRAMES PAINT
3/14/06 3/17/06 THRU 3/20/06 FIELD HOUSE STE. 106 (WALL BEHIND RECEPTION DESK) PAINT PAINT
3/14/06 3/17/06 THRU 3/20/06 LIB-5104 & 2444 (TOUCH UPS) PAINT PAINT
3/22/06 3/24/06 CRA-6145 PAINT PAINT
3/22/06 3/23/06 LIB-1105,1106,1107,1108,1109 PAINT PAINT
4/6/06 4/11/06 THRU 4/14/06 FH-GRAND SALON PAINT, TOUCH UP PAINT
4/6/06 4/11/06 THRU 4/14/06 LIB-2413 (TOUCH UPS) PAINT PAINT
4/24/06 FOLLOWING 6 - 8 WEEKS CRA-1ST & 3RD FLOOR + COURTYARD PAINT & DEMOLITION PAINT & DUST
4/27/06 5/1/06 THRU 5/5/06 LIB-3310, 2000, 2016,2200 & 1311 HALLWAY PAINT & PATCH PAINT
5/9/06 5/12/06 THRU 5/19/06 FH-GRAND SALON PAINT PAINT
5/9/06 5/22/06 THRU 6/2/06 LIB-1111 PAINT & PATCH PAINT
5/17/06 5/19/06 THRU 5/20/06 SCI2-208 AND STAIRWELL PAINT PAINT
5/19/06 5/22/06 THRU 6/2/06 UH-237, 257, 371, STAIR #2 - S388 & S488 PAINT PAINT
5/22/06 5/23/06 THRU 5/26/06 MH-422-451, 321-360, 226-257, 126-257 PAINT PAINT
5/23/06 5/25/06 THRU 5/30/06 FH-GRAND SALON PAINT PAINT
5/23/06 5/24/06 THRU 5/26/06 ACD-106, 108, 111 & 113 PAINT PAINT
5/26/06 5/30/06 (AFTER 5:30PM) CRA-STAIRS NEAR ELEVATOR #2 DEMOLITION CUTTING TORCH FUMES
5/30/06 6/02/06 THRU 6/03/06 SCI II-NORTH SIDE OF BUILDING (WILL AFFECT ALL FLOORS) PAINT PAINT
5/30/06 5/31/06 THRU 6/14/06 SCI-L10, S101, 107, 105, V208, L201, L203, V234, 201, 203, C205, L303, V340, 303, S301, C305, C304, C200, C104 PAINT PAINT
5/30/06 6/01/06 THRU 6/02/06 CRA- 6TH FLOOR PAINT PAINT
5/31/06 6/01/06 THRU 6/9/06 CRA-STAIRS NEAR ELEVATOR #2 DEMOLITION CUTTING TORCH FUMES
6/7/06 6/9/06 THRU 6/15/06 ACD-304,305,306 PAINT PAINT
6/8/06 6/13/06 THRU 6/15/06 SCI2-133 PAINT PAINT
6/12/06 6/14/06 THRU 6/15/06 CRA-L6048 (CORRIDOR BETWEEN ELEVATORS) PAINT PAINT
6/12/06 6/15/06 THRU 6/23/06 SCI-C200, 201, 203, L203, V208, V234, C205, S101, C106, L103, C104 & 105 PAINT PAINT
6/12/06 6/14/06 THRU 6/16/06 SCI-L303 & V340 PAINT PAINT
6/14/06 6/15/06, 6/16/06, 6/19/06 SCI-C304 PAINT PAINT
6/14/06 6/16/06 (AFTER 5:30) SCI-120 (MECHANICAL ROOM) PAINT PAINT
6/22/06 6/22/06 THRU 7/6/06 (EVENING HOURS) SMACC-2ND FLOOR PAINT PAINT
6/23/06 6/26/06 THRU 6/30/06 SCI-STAIRWELLS: S-102, S-202 & S-302 PAINT PAINT
6/28/06 THRU 6/30/06 COM-CORRIDOR 121, MEN'S RESTROOM 118 & FOOD COURT SEATING AREA 102 PAINT PAINT
6/29/06 7/6/06 THRU 7/7/06 MH-STAIRWELL #2 PAINT PAINT
6/30/06 7/5/06 THRU 7/6/06 USB-55H UNIVERSITY POLICE MEN'S RESTROOM PAINT PAINT
7/6/06 7/10/06 THRU 7/11/06 CRA-6623, 6201 & UH-324 PAINT PAINT
7/10/06 7/13/06 THRU 7/21/06 COM-CORRIDOR 121, MEN'S RESTROOM 118 & FOOD COURT SEATING AREA 102 PAINT PAINT
7/11/06 7/17/06 THRU 7/19/06 SCI2-306 PAINT PAINT
7/11/06 7/13/06 THRU 7/14/06 SCI-316 & 1ST FLOOR HALLWAY PAINT PAINT
7/18/06 7/26/06 THRU 7/27/06 CRA-6211 PAINT PAINT
7/18/06 7/21/06 THRU 7/22/06 SCI-316 PAINT PAINT
7/18/06 7/21/06 THRU 7/22/06 SCI-1ST & 3RD FLOOR HALLWAYS VINYL COVE BASE ADHESIVE
7/21/06 7/24/06 THRU 7/25/06 ACD-3RD FLOOR HALLWAYS PAINT PAINT
7/21/06 7/24/06 THRU 7/28/06 LIB-2402 & 3200 LOBBY PAINT PAINT
7/21/06 7/20/06 THRU 7/28/06 COM-CORRIDOR 121, MEN'S RESTROOM 118 & FOOD COURT SEATING AREA 102 PAINT PAINT
7/24/06 7/26/06 SCI-1ST & 3RD FLOOR HALLWAYS VINYL COVE BASE ADHESIVE
7/24/06 7/26/06 THRU 8/28/06 SCI-207, 316 & 105 PAINT PAINT
7/26/06 7/26/06 THRU 8/3/06 ACD-102, C202, C203,C204, 302A, C302, C304, 402A CORRIDOR, 319 PAINT PAINT
8/1/06 8/4/06 THRU 8/2/06 ACD-102, 115, 113, 111, C202, C203, C204, 302A, C302, C304, 402A CORRIDOR PAINT DOORS/FRAMES PAINT
8/4/06 8/7/06 CRA-5311D PAINT PAINT
8/8/06 8/8/06 THRU 8/11/06 FH-CORRIDORS PAINT PAINT
8/8/06 8/10/06 THRU 8/11/06 MH-CENTER STAIRWELL (S2) PAINT PAINT
8/14/06 8/14/06 THRU 8/22/06 CRA-1ST FLOOR PAINT PAINT
8/16/06 8/17/06 THRU 8/21/06 FH-CORRIDOR 459 & 1800, MEN'S & WOMEN'S VESTIBULE & LOCKERS, 342 RECEPTION PAINT PAINT
8/17/06 8/21/06 THRU 8/23/06 UH-C295, L294, L292, C394 & C398 PAINT PAINT
8/24/06 8/25/06 THRU 8/29/06 LIB-3105 & 3100 PAINT & CORNER GUARDS PAINT & ADHESIVE
8/28/06 8/28/06 THRU 9/1/06 SCI-VESTIBULE 97, 112, 114 & 116 PAINT PAINT
8/29/06 9/1/06 UH-371 PATCH & PAINT PAINT
9/5/06 9/5/2006 THRU 9/13/2006 CRA-STAIRWELL #1 HANDRAILS PATCH & PAINT PAINT
9/12/06 9/13/2006 THRU 9/15/2006 CRA-CORRIDOR 237 PATCH & PAINT PAINT
9/26/06 10/2/2006 THRU 10/4/2006 MH-421 & STAIRWELL #2 PATCH & PAINT PAINT
9/27/06 9/29/2006 KEL-3423 PATCH & PAINT PAINT
10/4/06 10/6/2006 THRU 10/9/2006 MH-STAIRWELL #2 2nd FLOOR SOFFIT PATCH & PAINT PAINT
10/4/06 10/6/2006 THRU 10/11/2006 CRA-6048 6th FLOOR ELEVATOR LOBBY, CRA-5303 PATCH & PAINT PAINT
10/10/06 10/12/2006 & 10/13/2006 MH-111 & STAIRWELL #2 2nd FLOOR SOFFIT PATCH & PAINT PAINT
10/23/06 10/23/2006 & 11/10/2006 CRA-1ST & 3RD FLOOR PAINT PAINT
11/6/06 11/8/2006 ACD-106 MEN'S RESTROOM PAINT PAINT
11/14/06 11/16/2006 & 11/17/2006 LIB-3004 THRU 3007 PAINT PAINT
11/14/06 11/17/2006 & 11/20/2006 THRU 11/22/2006 ACD-C-117, 119, S-103, 106 & 217 PAINT PAINT
11/14/06 11/17/2006 & 11/20/2006 THRU 11/22/2006 CRA-CORRIDOR 4002 PAINT PAINT
11/21/06 11/27/2006 & 11/28/2006 LIB-3303 PAINT PAINT
11/28/06 11/30/2006 THRU 12/2/2006 ACD-119 & 121 (FUMES MAY ENTER AIR INTAKES AND BE DETECTABLE THROUGHOUT BUILDING) VINYL COVE BASE ADHESIVE
11/28/06 12/1/2006 THRU 12/8/2006 CRA-4TH FLOOR CORRIDORS PATCH & PAINT PAINT
12/4/06 12/6/2006 THRU 12/7/2006 FH-COLUMN IN MAIN RECEPTION AREA PATCH & PAINT PAINT
12/14/06 12/18/2006 THRU 12/21/2006 CRA-6233 PATCH, PAINT & TILE ADHESIVE PAINT & ADHESIVE
12/18/06 12/20/2006 THRU 1/5/2006 LIB-3301 PATCH & PAINT PAINT
12/20/06 1/2/2007 THRU 1/17/2007 MH-STAIRWELL 2 "CHEMSTAIN" "CHEMSTAIN"
1/3/07 1/5/2007 THRU 1/17/2007 UH-240, UH-260, UH-270, UH-271, UH-272,
UH-273, UH-370, UH-439, & UH-441
PATCH & PAINT PAINT
1/3/07 1/4/07 CRA-6206 PAINT PAINT
1/3/07 1/5/07 THRU 1/8/07 CRA-6202, 6204, 6209, 6210, 6216, 6220, 6235 PAINT PAINT
1/4/07 1/8/07 THRU 1/12/07 MH-RESTROOMS PAINT PAINT
1/11/07 1/16/07 THRU 1/19/07 SCI2-ENTRY LOBBY-290 & CORRIDOR-291 PAINT PAINT
1/11/07 1/16/07 THRU 1/19/07 ARTS-CORRIDOR-192 & CORRIDOR-191 PAINT PAINT

WE APPRECIATE YOUR PATIENCE AND COOPERATION DURING THE OCCUPANCY OF THE NEW BUILDINGS